Retention - Third time lucky in attempt to abolish retention?

Whilst ‘pay when paid’ clauses are generally prohibited by the Construction Act 1996, this may be the reality for subcontractors where a main contractor is not willing to release their retention as a result of retention monies held back by an employer.

As a Private Members’ Bill is presented to Parliament calling for retention within construction contracts to be abolished, we look at what retention is, the issues it can cause, what the Bill provides, and what the alternatives might be.

What is retention?

Most building contracts and sub-contracts will contain a retention clause in them. The effect of a retention clause is that it allows an employer to hold back a percentage from payments otherwise due to the contractor. Retentions can also be used as a way of ensuring certain documentation is provided, such as performance bonds, parent company guarantees, and collateral warranties.

Commonly, retention is 3% or 5% of the interim payment due, with half of the retention being released after practical completion and the other half being released after the issue of the certificate of making good defects.

From an employer’s perspective, retentions perform a number of important functions, including reducing the risk that a contractor has been overpaid should they become insolvent during the works, providing for an amount of money that is not paid to the contractor that is available to apply to the additional costs of employing a third party contractor to complete the relevant works should the contractor become insolvent during the project, and providing a sum of money after practical completion that is only available to the contractor if it returns to site to rectify any defects in its works (and that can be used to pay a third party contractor if the original contractor fails to return to rectify these defects).

What are the potential issues with retention?

The use of retention arguably puts the contractor in a disadvantageous position and can cause them cashflow problems, particularly if the retention monies are unfairly held on to for too long. For example, in the case of DR Jones Yeovil Ltd v Stepping Stone Group Ltd, the contractor was still waiting for retention monies to be released by an employer three years after they had made good defects.

Whilst ‘pay when paid’ clauses are generally prohibited by the Construction Act 1996, this may be the reality for subcontractors where a main contractor is not willing to release their retention as a result of retention monies held back by an employer.

It is therefore often the smaller subcontractors and suppliers further down the contractual chain that end up bearing the cost of the retention being withheld. Retentions can also be difficult to extract from employers at the end of the project. If an employer raises a potentially weak counterclaim against that retention, it may not be worth the time and cost of fighting that counterclaim so contractors end up accepting that the retention is not paid, or accepting a deal where only a proportion of the retention is paid at a level lower than what the contractor may regard as its true entitlement.

Likewise, if the employer becomes insolvent retention monies will not necessarily be ringfenced and therefore may be paid to other creditors instead of being released to the contractor. For example, following the collapse of Carillion in 2018 it was discovered that the company was holding approximately £800 million in retention monies belonging to subcontractors. The JCT contracts reflect the concept that retention monies should be held on trust and that the employer can be requested by the contractor to set these monies aside in a separate account. However, these terms are often amended so that the employer owes no fiduciary duty to the contractor and to remove any obligation on the employer to hold retention sums in a separate account.

James Worthington

Partner Construction

+44 (0)20 7427 1070 james.worthington@crsblaw.com

The Construction (Retentions Abolition) Bill

There are clearly advantages to employers and funders from the deduction of retention, but also legitimate concerns from contractors about the effect they have on cash flow, the insolvency risk of their employer and the difficulties of recovering the retention at the end of a project.

These concerns from contractors are behind the proposals of the Construction (Retentions Abolition) Bill introduced to Parliament as a Private Members’ Bill by Lord Aberdare in October 2021. The Bill aims to amend the Construction Act 1996 by making any clause enabling a payer to withhold retentions in a construction contract void. It would also mean any existing retentions would be due to be paid in full no later than 7 working days after they were due but withheld.

The definition of “retentions” under the Bill is quite wide. It may capture not only retention that is withheld from an interim payment but also retention held until certain documentation required by the construction contract is provided, for example performance bonds, parent company guarantees, collateral warranties and as-built drawings.

What are the alternatives?

Abolishing cash retentions would clearly be welcomed by the supply chain in construction projects. However, employers would still want some form of security for the risk of insolvency and non-performance (in particular, a failure to rectify defects). Some potential alternatives to retention are:

  • The introduction of mandatory defects liability insurance where contractors would be incentivised to complete works and amend defects through reductions in premiums.
  • Longer payment terms. However, these can also bring significant disadvantages to contractors.
  • Increased use of performance bonds and retention bonds. However, these carry their own costs.
  • The introduction of a retention protection scheme to provide greater protection of retention monies for contractors. From a contractor’s perspective, this may not resolve the cash flow issues caused by retention being deducted, but it should reduce the risk that a retention will be lost if an employer becomes insolvent.

Conclusion

The Construction (Retentions Abolition) Bill follows two other recent attempts to introduce legislation regarding retentions through Private Members’ Bills.

In 2017, the Construction Industry (Protection of Cash Retentions) Bill did not get past its first reading. In 2019, the Construction (Retention Deposit Schemes) Bill failed to pass because of a lack of Parliamentary time – this was even with the backing of nearly 300 MPs and at what would have seemed like an opportune time, just after the collapse of Carillion in 2018.

The new Private Members’ Bill does not yet have a fixed date for a second reading in the House of Lords and will potentially suffer the same fate as the Private Members’ Bills before it.

And if it were to be passed? The legislation would not come into force until 1 January 2025 and it is likely that the financial burden of any alternatives would still ultimately be passed downstream from employers to contractors and subcontractors.

Abolishing cash retentions would clearly be welcomed by the supply chain in construction projects. However, employers would still want some form of security for the risk of insolvency and non-performance (in particular, a failure to rectify defects).

Alumni Legal Notices Accessibility Privacy Notice Fraudulent or 'scam' communication Complaints Procedure COVID Secure Certification Pricing Information

© Charles Russell Speechlys 2022. Solicitors Regulation Authority number 420625.